Work Order Reports

Top

 

The work order reports have to do with work orders entered in the Maintenance function.

 

Each report can be limited to different subsets of vendors, owners, units, tenants as well as date ranges using the selection fields on the Work Order Report selection screen.

 

Work Order Report Fields

Report Name

Choose the report name from the Find List. The reports are limited to specific work order statuses.

Sort Order

Choose the sort order you want for the report from the Find List. Choices include Site, Unit, Ledger, Management Group, Vendor, Building, Unit Type, Property Manager).

Report Date

Enter the date range you want for the report. Only work orders falling within the date range will be considered.

Restrict To

The report can be limited to a specific vendor, owner, tenant, unit, management group, property manager or profile list.

Limit to

The report can be limited based on the information entered in the work order in any of the following fields:

Priority

Vendor

Maintenance Type

Asset Type

Brand

Date Ranges

The report can be limited based on dates in the work order that fall within the range entered here in any of the following fields:

Problem Reported

Vendor Notified

Date Required

Work Started

Work Completed

 

Work Order Summary Report

This report lists those work orders with a status corresponding to the title of the report.

 

Open: Vendor Notified, Estimate, Unassigned, Out for Bid, In Progress

Pending: Estimate, Out for Bid

Completed: Invoiced, Completed, Resolved

Reported: All

Resolved: Invoiced, Resolved

 

Information is provided on the following:

Work Order ID

Site and Description - the address of the unit and the

problem description from the work order

Vendor

Dates: Reported, Required, Notified, Started

Priority

 

Work Estimates report

This report will list any work order that has an estimated amount which is held back when doing distribution checks. All work order statuses except Invoiced and Resolved are included. The work order report screen has an "Estimate Exceeds" field which will limit the report to those work orders with an estimate greater than the Exceeds amount.